You are currently viewing Keeping Turbines Available and Reliable
Mamoso May, Asset Management Standing Committee Chairperson at the South African Wind Energy Association (SAWEA)

Keeping Turbines Available and Reliable

Engineering, assembling, and installing wind turbines for power generation is only the beginning of the asset lifecycle. Once commissioned, the focus shifts to protecting availability, production and long-term asset value through an Operations & Maintenance (O&M) strategy that responds to the condition and operating history of the asset.

Mamoso May from the South African Wind Energy Association (SAWEA) illustrates to Machinery Maintenance Matters what a suitable O&M strategy entails.

In South Africa, through the Renewable Energy Independent Power Producer Procurement Programme (REIPPP), the addition of more than 30 utility-scale wind farms to the electricity grid has increased generation capacity to meet demand.

As of December 2025, South Africa had nearly 4 GW of installed wind capacity, making effective operations and maintenance increasingly important as the operating fleet grows and matures.

As South Africa’s operating wind fleet grows and matures, maintaining high levels of technical availability while controlling lifecycle cost becomes increasingly important.  This requires effective operations and maintenance (O&M) strategies, states Mamoso May, Asset Management Standing Committee Chairperson at the South African Wind Energy Association (SAWEA). 


What happens when a wind turbine fails?

To get a sharper perspective on the significance of effective O&M strategies, one has to consider the impact of turbine failure: lost energy generation and the potentially high cost of restoration.

i. GWh of lost energy generation

May demonstrates the impact of lost generation: “On average, a turbine experiencing a major component failure may be offline for around 40 days. This results in approximately 1.1 GWh of lost energy generation for a 3 MW turbine and an estimated revenue loss of approximately R2 million, assuming an electricity tariff of R1.75/kWh.”

The situation can get worse, she adds: “Where a component has to be imported or a suitable crane is not immediately available, the outage can extend considerably beyond this. For instance, a 90-day outage, using the same assumptions, would mean roughly 2.5 GWh of foregone generation and R4.4 million in lost revenue.”

ii. The cost of restoration

Beyond the loss of generation, there is the cost of the actual repair, component replacement, specialist labour or crane mobilisation, just to cite the main issues.

These impacts reinforce why O&M decisions should be made with clear understanding of production exposure, component criticality and remaining life of the asset.

Developing an effective O&M strategy

At the outset, there is a misconception that there is some kind of one-size-fits-all manual that can be universally adopted and implemented for O&M strategies for wind turbines in South Africa.

On the contrary, the country does not have one type of wind farm operating under one set of conditions, May clarifies. Actually, the same applies across the international wind industry. Thus, the development of O&M strategies for individual wind farms should be approached from this perspective.

This becomes clear when the factors affecting the reliability and availability of individual assets are considered.

Factors vital in developing a relevant O&M strategy

Specifically, May brings up the following factors that are vital in developing an O&M strategy: different environmental conditions that wind assets are exposed to, asset age, and supply-chain considerations, particularly component sourcing.

a. The environment

A wind turbine at a coastal site, for example, may have to deal with high exposure to corrosion, salt and moisture that would not necessarily be encountered at an inland site. Other sites have dust, temperature extremes, lightning or difficult weather conditions that affect when maintenance can actually be carried out.

b. Age

Then, there is the issue of the age and technology of the fleet. For instance, some of the earlier REIPPPP wind farms are now well into their operating lives, while much newer turbine platforms are entering the market. These differences mean that O&M strategies have to evolve according to the age, technology and operating history of each asset.

May remarks: “You cannot maintain a ten-year-old turbine in exactly the same way you approached it when it was new. By that stage, its history matters. You know which components have been problematic, which faults keep returning and where the asset is beginning to show its age.”

c. The supply chain

In one way or another, supply-chain risk has an impact on wind turbine maintenance. While the exposure varies between countries, in South Africa it has a huge impact, due to the fact that the country still imports many specialist components.

So, sometimes the repair itself may not be the biggest problem, May argues, indicating where the real challenge could lie: “The problem can be getting the part into the country, getting the right specialist to site, or securing a crane when you need one. As a result, a wind turbine can remain out of service for significantly longer than the technical repair itself requires.”

Understanding root causes of lost production

Once lost production has been identified, the next step is to determine its root cause and direct resources accordingly, advises May. “We need a more accurate understanding of what is driving lost production. This is because turbine downtime, grid outages and curtailment have different causes and require different interventions.”

Understanding the different causes is important because not all lost production can be addressed through maintenance. The bottom line is: if all lost energy is treated as a single issue, maintenance resources may be directed towards the wrong problem.

Diagnosing the root cause of failure

May cautions that South African turbines do not necessarily experience unique failure modes. What often differs is the environment around the failure and establish how quickly the turbine can be returned to service.

Particularly, she points out, it is important to pay attention to blades and leading-edge damage, lightning protection systems, pitch and yaw systems, gearboxes, bearings, generators, converters, hydraulics, cooling systems, transformers, drive trains, and various sensors and control components.

In the end, these checks provide the basis for determining whether a developing fault can be addressed through early intervention or whether a more extensive repair is required.

Importance of early intervention

May highlights the importance of early intervention. “A minor defect can often be repaired relatively easily when detected early. If left unattended, however, it can develop into a significant structural problem requiring more complex and costly repairs.”

For instance, detecting changes in vibration, oil condition, temperature trends and other indicators can provide early indications of deterioration before a component fails.

Another point worth mentioning is that the component that fails most frequently is not necessarily the one that presents the greatest operational risk, notes May. “A sensor may fail regularly but can usually be replaced quickly. On the other hand, a gearbox or generator may fail less often, but a single failure could result in months of lost production if replacement parts must be sourced internationally, primarily from Europe, and specialist labour and a large crane are required.”

This means that maintenance priorities should not be based simply on failure frequency. The potential consequence of a failure also needs to be considered.

Effectiveness of a maintenance programme

At the end of the day, the effectiveness of a maintenance programme depends on whether warning signs are detected, correctly interpreted and acted upon in time.

Key Questions When Shaping a Turbine O&M Strategy

In developing a specific turbine operations & maintenance strategy, May suggests seeking answers to the following questions:

· What has happened to that turbine over the last five or ten years?

· Which alarms keep coming back?

· Which components have already been replaced?

· What is the condition of the blades?

· What is the oil telling you?

· What does the vibration data show?

· Are there recurring temperature issues?

· Are all the condition-monitoring systems even working?

Those are the questions that begin to shape a useful maintenance strategy.

Details like age, turbine type, site conditions, maintenance history, SCADA data, component condition, operating hours, warranties, access to spares and the expected remaining life of the project all matter.

Technical health baseline

On an older asset in particular, it is worthwhile to stop periodically and establish a proper technical health baseline, May proposes. That may involve blade inspections, borescope inspections, oil analysis, vibration data, electrical testing, alarm analysis and a review of repeated failures, she says. Based on this, a decision can be made about where the real risks lie.

Commercial decision

Besides that, it becomes a commercial decision, indicates May. This is particularly the case where the lack of a certain component could leave a turbine standing for three or four months because there is no replacement available locally.

“In cases where having no component could result in downtime, then keeping that component in stock makes sense. The component is no longer just an expensive spare sitting on a shelf. It may be insurance against several months of lost generation.”

As a final point, in general, an O&M strategy has to evolve with the asset, states May. “The biggest mistake would be to write an O&M strategy once and leave it unchanged for years. The strategy should move with the asset.”